As per the current status, there is only one city water supply connection available. The local zone stated that the current water supply pressure is less than 0.2Mpa, they are now planning a installation of pump station which is under construction and schedule to complete by mid year of 2020, which will bring the pressure to 0.25Mpa. However, it is the GC’s responsibility to confirm with HED Zone and verify the information on site.There are three city sewage discharge connections proposed. It is the GC’s responsibility to check with HED Zone for the detailed information, such as pipe size, connection levels and so on, and verify the information on site.