Hi Team,Mike Ferris has quarantined all stock (219pcs) from both lines. DuraTech has confirmed they have 350pcs in their warehouse that are also nonconforming. They have immediately placed a work order for 350pcs and will get back to me before 2:30pm today with their set timelines for replacements and qty. Here are the three replacement scenarios on the table now. Again, I will have a better idea after their scheduler is back at 1pm with set timelines.1. Work Order dropped today, *estimated* replacement date → Wed (21Oct), Thursday (22Oct) next week.2. From the 350pc work order, they can ship partials to satisfy orders in Wuxi/MSN3. I asked if a small partial order can be placed now to satisfy Wuxi and MSNa. If confirmed, they will need to know the number of partials needed for Wuxi and MSN4. They may be able to print in the missing location on their nonconforming 350pcs currently in stock a. They are trying now to see if it’s feasible i. I asked to see what they look like prior, will forward to team..