Successful completion of the PLANT PERFORMANCE TESTS except the demonstration of noise level and effluents conditions, in accordance with the CONTRACT or, where applicable, the LIQUIDATED DAMAGES have been paid. THE successful demonstration of noise level and effluent conditions shall be proved by CONTRACTOR not later than 6 (six) months after PROVIONAL ACCEPTANCE.