1.Visit at site
2.Organization of the site for erection activities and presence of Engitec personnel during erection
3.Planning of erection works based on the equipment available at site and on the way to site
4.Planning of delivery at site of the equipment in Teli’s scope
5.Documentation of local supplier for the main equipment in Teli’s scope (PK-870; CR-750; SI-140/421/706; PK-140)
6.Final drawings by Teli of the crystallizer area for final check
7.Discussion of the documents submitted by Engitec with the sub – contractor in charge of erection and possible clarifications
8.Planning of the remaining shipments based on the progress and conditions at site