To explore the perimeter of the site sealing ditch, determine the depth and position of the clay water curtain, the stop curtain using a double row of clay sealwall, the effective thickness of about 1 m, depth of about 8 to 9 m.<br>The method of exploration is to lay the exploration point according to the 50 m spacing on the mid-line of the stirring pile construction, the depth of the permeable layer changes greatly or the area where the coarse sand layer exists, and the distance of the exploration point is arranged according to the 20 m spacing. After the exploration, the construction drawing of the mixing pile is arranged to make the deep reference map of the mud mixing pile construction.