As per our discussion during the meeting on 10/05/2019, the preliminary manual and drawings of the Auxiliary Transformer which passed to us are considered not to be the final manuals. After the completion of the whole project, JV should provide full sets of Final Manual and Drawings, Quality Manuals, Test and Commissioning Reports, Certificates, etc., of the complete project in accordance with the Contract Specifications.Regarding to the Spare Parts, please provide a detailed list as follow:The list of proposed spare parts or spare equipment must include description, must identify completely the spare and must refer to the respective drawing and item on the drawing of the equipment included on maintenance manual. Also, it must include the Functional Location Code (KKS) of all the equipment where the spare is used.