As of yesterday, we have successfully removed all four filters left in the natural gas pipeline, and this afternoon we have completed all flanges connectivity and leak testing. Therefore, it is planned to restart the 10 inch natural gas pipeline moisture testing work tomorrow at 10 a.m., given the relatively low nitrogen production on our side, or do you want to introduce nitrogen blowing to our side of MLNG, which is expected to be completed in 2 days and 2 nights. Please help coordinate the plan, thank you.