Within 42 days after the contractor became aware (or should have known) of the event or circumstance giving rise to the claim, or within such other period as may be proposed by the contractor and approved by the engineer, the Contractor shall send to the design a detailed claim including full supporting details of the basis of the claim, the extension of time and / or additional payment required.