Construction can only continue after confirming that the temperature of the concrete mixture entering the mold does not exceed 30°C. <br>⑤ Calculate the slump loss value of concrete during transportation under high temperatures, remind and supervise the on-duty tester, and reserve the slump loss value. <br>⑥ Once the temperature of the concrete mixture is found to exceed the indicator during the construction process, the construction site should be immediately urged to check the cause and take effective cooling measures. <br>⑦After the concrete pouring is completed, check the grouting work of the initially poured concrete and check whether there are shrinkage cracks from the initial setting to the final setting. Check the template filling port