⑧在养护期内应经常浇水、使混凝土表面始终保持潮湿。养护期结束前后,应及时检查混凝土表面for any收缩裂缝。如发现收缩裂缝,应适当增加浇水的英语翻译

⑧在养护期内应经常浇水、使混凝土表面始终保持潮湿。养护期结束前后,应及

⑧在养护期内应经常浇水、使混凝土表面始终保持潮湿。养护期结束前后,应及时检查混凝土表面for any收缩裂缝。如发现收缩裂缝,应适当增加浇水养护时间。模板只有在按规定混凝土达到规定强度后方可拆除。此外,根据夏季施工要求,只有混凝土芯部温度达到最高值并确认处于下降阶段,方可拆模。
0/5000
源语言: -
目标语言: -
结果 (英语) 1: [复制]
复制成功!
⑧During the curing period, water should be frequently applied to keep the concrete surface moist at all times. Before and after the end of the curing period, the concrete surface should be checked promptly for any shrinkage cracks. If shrinkage cracks are found, the watering and curing time should be appropriately increased. The formwork can only be removed after the concrete reaches the specified strength as specified. In addition, according to summer construction requirements, the formwork can only be removed when the concrete core temperature reaches the highest value and is confirmed to be in the declining stage.
正在翻译中..
结果 (英语) 2:[复制]
复制成功!
⑧ During the curing period, frequent watering should be carried out to keep the concrete surface moist at all times. Before and after the end of the curing period, the concrete surface should be promptly inspected for any shrinkage cracks. If shrinkage cracks are found, the watering and curing time should be appropriately increased. The formwork can only be removed after the concrete reaches the specified strength according to regulations. In addition, according to summer construction requirements, only when the temperature of the concrete core reaches the highest value and it is confirmed that it is in the declining stage, can the formwork be removed.
正在翻译中..
结果 (英语) 3:[复制]
复制成功!
Today in the curing period should be often watered, so that the concrete surface is always wet. Before and after the end of the curing period, the shrinkage cracks on the concrete surface should be checked in time. If shrinkage cracks are found, the water curing time should be appropriately increased. The formwork can only be removed after the concrete reaches the specified strength according to the regulations. In addition, according to the requirements of summer construction, only when the temperature of the concrete core reaches the highest value and is confirmed to be in the descending stage can the formwork be removed.
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.