The Contractor acknowledges that it has a technical confidence in all supplied equipment under prevailing operational conditions (in line the minimum and maximum conditions of the local Building Code BNbD 23-01-09 as updated from time to time and other Applicable Documents). The Contractor acknowledges that it has designed the Facilities to achieve the level ofperformance and output of the power plant specified in the Contract, based on operating conditions (including solar irradiation) as defined in the local Building Code BNbD 23-01-09 as updated from time to time. The Contractor shall oversee the operation and maintenance support of the plant for a duration of two years following Completion to prove operational management and output quality.The Employer expects the Contractor to construct the plant on a turnkey basis including required grid connection assets. The Contractor will operate the plant for the duration of twoyears following Completion to prove operational management and output quality.