1. Select task - Masonry , N2. Open up Task Properties General3. Under Durations, change the Remaining Duration value to 7d. The % Complete is updated.4. Press F9 on the keyboard to reschedule the downstream tasks.5. In the Gantt Chart, the blue task bar extends beyond its Planned Duration represented by the green line