Thank you for the update on the project procurement status!Good to see the progress in Yugan and Shangli counties - thanks to PPMO for the steadfast follow-up and support.However, the risk of not being able to complete the project activities (LMP contracts and some works contract) appears to have further increased, with only 21 months left before Loan Closing Date of December 31, 2022. A number of contracts have an implementation period of 18 months or longer, and the two contracts in Poyang county are still at bidding document preparation stage. This is of great concern to the Bank.We therefore would like to request the PPMO and the county PMOs concerned (a) to further step up their efforts to conclude all remaining contract procurement before June 2021; and (b) to update us WEEKLY on the procurement progress, until all remaining contracts are signed.If you think it is necessary to have a joint (virtual) meeting with Poyang county chiefs, please organize one later next week.Please be assured of our continued support where needed.