After entering the construction site, the site shall be leveled first, and the root soil, weeds, reeds, etc. shall be removed by excavator. Prepare construction water and electricity interface.<br>Before setting up the plastic plate, use the level to measure the elevation of the ground according to the grid of 20 m × 20 m, the allowable construction deviation of the surface elevation is ± 50 mm, and report the data to the owner and the supervising engineer for acceptance.<br>