In paragraph 40, for the spare parts, specify:At the TCP stage, the equipment supplier provides:- A preliminary list of spare parts for the stages of installation, commissioning and 2 years of warranty operation;- A preliminary list of special tools for the stages of installation, commissioning and further maintenance of equipment.At the WCD stage, the equipment supplier provides:- Formed lists of spare parts, taking into account the analysis of the supplied equipment for the stages of installation, Commissioning and 2 years of warranty operation for approval by the contractor and the customer (according to the unified form of the project);- Formed lists of spare parts, taking into account the analysis of the supplied equipment for major repairs for approval by the contractor and the customer (according to the unified form of the project);- Formed taking into account the analysis of the supplied equipment of a special tool (according to the unified form of the project);