List of improvement points: Product results for the first prototype parts (semi-finish till grinding step) : Results looks good,but no capability checks or equivalent were done by SUMITOMO team in order to confirmthat no improvements are needed.Hitachi request is to have a capability study on 30 parts for all the characteristics. On this transfer project, that will correspond to a total increase of 10% of the plant volume,only people from the plant are involved. No corporate people, that can work at 100% on theproject, are today affected in the plant as support. Hitachi request is to receive the list of the corporate support list. The control plan draft seen in SUMITOMO WUXI is not taken in account the currentdocument already implemented in SUMITOMO Germany. The document was built locally. Hitachi request is to receive evidences of the implementation of regular meetingsbetween the 2 plants (planning …) & to receive the updated CP by 2 weeks.