Yesterday we have taken out three filters from the 10" LNG trunk line. This afternoon we also completed the connection and leakage test of all flanges. Therefore, we plan to start cleaning the 10" LNG pipeline at 10 o'clock tomorrow morning. Then we want to introduce nitrogen from your MLNG to the tigergas side for moisture testing. It is estimated that it will take two days and two nights. Would you please help us to coordinate this cleanup? If you have any questions, please let me know. Thank you.