4. Finalization of Early Production Containment The supplier will be able to close Early Production Containment procedure when - scope/duration specified in point 3 are fulfilled and exit criteria is met for all LCP-characteristics - all corrective actions are completed and verified - Early Production Containment results are implemented in Process-FMEA If the supplier is unable to meet the exit criteria, the supplier should continue Early Production Containment procedure until all open points are solved to the satisfaction of both the supplier and Bosch. The decision to close Early Production Containment is carried out and discussed in a meeting between the supplier and Bosch after all required documentation is submitted. The finalization of Early Production Containment is determined on the LCP with the signature of the Supplier Quality Engineer and the responsible PMQ-engineer.