The warm-up temperature of the steel pipe is not easy to reach the temperature requirements and the phenomenon of rapid temperature reduction, after the completion of sand blasting rust removal, set up a special person in advance with a baking put to the pipe surface continuously and evenly heated, when the anti-corrosion worker to carry out the anti-corrosion filling operation of the weld, and then move to the next port to preheat in advance. In order to offset the heat dispersion failure in low temperature environment, when preheating the weld, the upper limit of the preheat temperature requirement should be reached, the temperature control is measured by infrared thermometer, and 8 points are measured along the circumference.