Hi All,With the FW20 production simulation is coming to end, I would like to highlight some area that we need pay attention and do improvement in future.1. Smart tools&jigs need be used in simulation. Only saw one smart tool to be used in APE that I attended 12 times production simulation in different factories, this didn’t meet our expectation. All of you attended the smart tools&jigs workshop last year, I do hope you can follow your action plan, find and work with external resources to keep improvements on this area. Expecting to seeing the good performance from all of you in SS21. 2. Don’t combine the production simulation with first production, pls do simulation before one week or 10 days before first production. 3. During production simulation, pls exactly follow the layout that IE provided, make sure the machine and operator are set well. 4. Treatment simulation is not mannered, just showed us the process. We want to focus on this area in SS21 and pls follow below steps for SS21 . I will talk with you one by one for my requirements.*Pls collect the data at SMS stage, follow SOP to collect the CT for each process, daily output and RFT *Follow the process CT, Work with subcontractor to make out the optimized layout for each process*During simulation, pls put the data and optimized layout on the board to let’s have clear information. Above are the highlights that I hope we can make improvement and be prepared well for SS21. Many cases already approved the good simulation trial can bring the high efficiency in very short time at first month production, let’s really focus on it and bring value to your factory.