As per your email on 20/11/2019, we’ve been noticed that the basements and wheels of the furnaces have been released to the site. Thank you for the advice.We would ask you the status of the basements foundation modifictations? Did you start to modify the foundations? When can we expect will be ready? Another very important point is to receive the drawings with the new measures so we can check the hold points on our drawings we sent to Teli.Last but not least, please note that we need to receive 10 days in advance your request to have Mr. Sacchettini available to fly to the site. In that occasion please also confirm the availabity of the tools necessary for basements installation.