Window & Facade
- Curtain Wall
- The cast-in has been installed from level 6 to 13 on Tower C;
- The cast-in has been installed from level 6 to 16 on Tower D;
- Curtain walls on North elevation have been installed from level 7 to level 13;
- Curtain walls on East elevation have been installed from level 7 to level 13;
Sliding Door
- The external frames have been completed from level 6 to 16 on Tower C;
- The internal frames have been completed from level 6 to 16 on Tower C;
- The external frames have been completed from level 6 to 15 on Tower D;
Perforated Screen
- The steel frames and brackets have been installed 60% on Tower E level 14 to level 16;
- The folded perforated screen will be finished from level 14 - level 16 on Tower E;
- The folded perforated screen will be finished from level 14 - level 16 on Tower C;
Aluminium Cladding
- The aluminium cladding has been installed from level 6 to 13 on Tower E Western elevation; The aluminium cladding has been installed from level 6 to 13 on Tower D Eastern & Western elevation; The aluminium cladding has been installed from level 6 to 13 on tower C Eastern elevation; The aluminium cladding has been installed from level 1 - level 5 on tower C southwest corner;
- Balustrade bottom track has been installed on level 7 - level 13 on Tower E.
Services
- Plumbing cold and hot water & gas pipes Rough-In work on level 9 - 14, Tower E. Level 9 - 13, Tower D.
- Mechanical: Install ducts, refrigeration pipes on level 8 - 13, Tower E. Level 8 - 12, Tower D.
- Electrical: Tower C D E, Rough-In, level 8 - 12 is completed.
- Fire service: Install sprinkler pipes level 10 - level 16 on Tower C & D, fire hydrant level 6 - level 18, Tower D is completed.
- Lift: On-going installation of Tower lift in Tower C & D, lift in Tower E is commissioning.
- Garbage Chute: Chute Section all complete in Tower C D E.
Inferior Fit-out
- Plastering: Tower 5 level 6 to level 14 stud works completed and level 6 - 13 P60 external wall in progress; level 6 - 10 internal plastering in progress; Tower 4 Stud works to level 6 - level 12 completed;
Tower 3 Stud works to level 6 - level 13 completed.
- Waterproofing:
Screeding and waterproofing of balcony and planter box on level 6 Tower C.
Screeding and waterproofing of balcony and planter box on level 14 Tower D.
- Painting: Ceiling texture paint completed in the balcony area from level 7 to level 16 of Tower E;
Ceiling texture paint completed in the balcony area from level 7 to level 16 of Tower C.
- Blockwork: Service riser block work completed from level 15 to level 16;
- Green facade: Plants of podium level car par pre-grown has been started.
- Tiles: Scheduled to commence end of this Monday on Tower 5.
- Kitchen: Level 6 - level 7 Cabinets schedule to deliver to site end of this Month
To view photos, please click the following link: https://www.mdkholding.com/copy-of-riverina-pcg-june-2019
Notification will be provided when practical completion is obtained from the builder at which point we will commence bank valuations and final purchaser inspections.
* timeline subject to change without notice.
Late Settlement Consequences
Once the settlement has been triggered, you will only have a limited amount of time to settle your property. If you do not settle on time, penalty charges will be imposed and the incentives agreed to by the vendor may be withdrawn.
Warmest regards,
Jessica Yii
Settlement Team