Window & Facade- Curtain Wall- The cast-in has been installed from lev的简体中文翻译

Window & Facade- Curtain Wall- The

Window & Facade
- Curtain Wall
- The cast-in has been installed from level 6 to 13 on Tower C;
- The cast-in has been installed from level 6 to 16 on Tower D;
- Curtain walls on North elevation have been installed from level 7 to level 13;
- Curtain walls on East elevation have been installed from level 7 to level 13;

Sliding Door
- The external frames have been completed from level 6 to 16 on Tower C;
- The internal frames have been completed from level 6 to 16 on Tower C;
- The external frames have been completed from level 6 to 15 on Tower D;

Perforated Screen
- The steel frames and brackets have been installed 60% on Tower E level 14 to level 16;
- The folded perforated screen will be finished from level 14 - level 16 on Tower E;
- The folded perforated screen will be finished from level 14 - level 16 on Tower C;

Aluminium Cladding
- The aluminium cladding has been installed from level 6 to 13 on Tower E Western elevation; The aluminium cladding has been installed from level 6 to 13 on Tower D Eastern & Western elevation; The aluminium cladding has been installed from level 6 to 13 on tower C Eastern elevation; The aluminium cladding has been installed from level 1 - level 5 on tower C southwest corner;
- Balustrade bottom track has been installed on level 7 - level 13 on Tower E.

Services
- Plumbing cold and hot water & gas pipes Rough-In work on level 9 - 14, Tower E. Level 9 - 13, Tower D.
- Mechanical: Install ducts, refrigeration pipes on level 8 - 13, Tower E. Level 8 - 12, Tower D.
- Electrical: Tower C D E, Rough-In, level 8 - 12 is completed.
- Fire service: Install sprinkler pipes level 10 - level 16 on Tower C & D, fire hydrant level 6 - level 18, Tower D is completed.
- Lift: On-going installation of Tower lift in Tower C & D, lift in Tower E is commissioning.
- Garbage Chute: Chute Section all complete in Tower C D E.

Inferior Fit-out
- Plastering: Tower 5 level 6 to level 14 stud works completed and level 6 - 13 P60 external wall in progress; level 6 - 10 internal plastering in progress; Tower 4 Stud works to level 6 - level 12 completed;
Tower 3 Stud works to level 6 - level 13 completed.
- Waterproofing:
Screeding and waterproofing of balcony and planter box on level 6 Tower C.
Screeding and waterproofing of balcony and planter box on level 14 Tower D.
- Painting: Ceiling texture paint completed in the balcony area from level 7 to level 16 of Tower E;
Ceiling texture paint completed in the balcony area from level 7 to level 16 of Tower C.
- Blockwork: Service riser block work completed from level 15 to level 16;
- Green facade: Plants of podium level car par pre-grown has been started.
- Tiles: Scheduled to commence end of this Monday on Tower 5.
- Kitchen: Level 6 - level 7 Cabinets schedule to deliver to site end of this Month

To view photos, please click the following link: https://www.mdkholding.com/copy-of-riverina-pcg-june-2019

Notification will be provided when practical completion is obtained from the builder at which point we will commence bank valuations and final purchaser inspections.

* timeline subject to change without notice.






Late Settlement Consequences
Once the settlement has been triggered, you will only have a limited amount of time to settle your property. If you do not settle on time, penalty charges will be imposed and the incentives agreed to by the vendor may be withdrawn.

Warmest regards,
Jessica Yii
Settlement Team



0/5000
源语言: -
目标语言: -
结果 (简体中文) 1: [复制]
复制成功!
窗门面<br>-幕墙<br>-的铸在已经从6级向安装13上C座; <br>-铸入已经从6级向安装16上塔d; <br>-北海拔幕墙已经安装了7级至13级; <br>-东海拔幕墙已经安装了7级至13级; <br><br>推拉门<br>-外部帧已经被从6级完成16上C座; <br>-内部帧已经完成了从6级到16 C座; <br>-外部帧已经完成了从6级到15上塔d; <br><br>穿孔的屏幕<br>-的钢框架和支架已经安装的60%上塔E级14成水平16;<br>-折叠穿孔屏幕将来自14级完成-在塔E 16水平; <br>-折叠穿孔屏幕将来自14级完成-在C座16水平; <br><br>铝覆层<br>-铝包层已经从6级向安装13上E座西视图; 铝包覆层已经从6级向安装13上塔d东西部正视图; 铝包覆层已经从6级向安装13上C座东视图; 铝包覆层已经从电平1安装- 5级上C座西南角; <br>-栏杆底部轨道上已经安装了7级- 13级上塔E. <br><br>服务<br>-管道冷热水和天然气管道排水管工作在水平9 - 14,塔E.等级9 - 13,塔D.<br>-机械:8级安装管道,制冷管道- 13,塔E.等级8 - 12,塔D. <br>-电气:塔CDE,排水管,8电平- 12就完成了。<br>-消防服务: -在塔C&d,消火栓6级16级-安装喷淋管10级18级,塔d完毕。<br>-提升:在正在进行安装塔电梯的大厦C&d,电梯在塔E的调试。<br>-垃圾滑道:斜槽部都完全在大厦CD E. <br><br>劣质装修情况<br>-抹灰:5座6级14级螺栓工程完成,6级- 13 P60外墙正在进行中; 水平6 -正在进行10内部抹灰; 塔4梭哈工程等级6 -完成电平12; <br>3座梭哈工程6级-完成13级。<br>-防水:<br>刮平和阳台和种植箱在水平6塔C的防水<br>刮平和上水平14塔D.阳台和培植箱的防水<br>-绘画:天花板质感涂料在阳台区域完成了从7级到E座16水平; <br>天花板的纹理涂料在阳台区域完成了从7级到塔C的16级<br>-砌块墙:服务提升板工作从15级完成16水平; <br>-绿色的门面:讲台级车看齐预生长的植物已经开始。<br>-瓷砖:订于5座本周一结束<br>-厨房:等级6 - 7级柜时间表投放到该月的网站到底<br><br>要查看照片,请点击以下链接:HTTPS://www.mdkholding。 COM /复制的,Riverina的-PCG日至2019<br><br>当从在这一点上,我们将开始银行的估值和最终购买者检查建造者获得实际完成将提供通知。<br><br>*时间表如有更改,恕不另行通知。<br> <br> <br> <br> <br> <br> <br>后期结算后果<br>一旦结算已被触发,您只能在有限的时间量来解决你的财产。如果不及时解决,罚款额会有所规定,并由卖方同意的激励可能会被取消。<br><br>向那,<br>杰西卡的Yii <br>结算队
正在翻译中..
结果 (简体中文) 2:[复制]
复制成功!
窗户 + 立面<br>- 幕墙<br>- 铸件已安装在 C 塔的 6 至 13 层;<br>- 铸件已安装在D塔的6至16层;<br>- 北高地的幕墙从7级安装到13级;<br>- 东高地的幕墙从7级安装到13级;<br><br>拉门<br>- 外部框架已在 C 塔的 6 至 16 层完成;<br>- 内部框架已在C塔6至16层完成;<br>- 外部框架已在D塔6至15层完成;<br><br>穿孔屏幕<br>- 钢架和支架已安装在 14 至 16 层的 E 层 60%;<br>- 折叠穿孔屏幕将从 14 级 - E 层 16 级完成;<br>- 折叠穿孔屏幕将从 C 塔的 14 级 - 16 级完成;<br><br>铝包层<br>- 铝包层安装在E塔西高地的6至13层;铝包层已安装在D塔东-西高程的6至13层;铝包层安装在C塔东高地的6至13层;铝包层从1层安装到C塔西南角的5层;<br>- 巴鲁斯贸易底部轨道已安装在7层 - 13级在塔E。<br><br>服务<br>- 管道冷热水和煤气管道粗糙工作在9-14层,塔E.9-13,塔D。<br>- 机械:在8-13层安装管道、制冷管道,8-12层,D塔。<br>- 电气:塔 C D E,粗加工,8 - 12 级完成。<br>- 消防服务:在 C + D 塔上安装洒水管道 10 级 - 16 级,消防栓 6 级 - 18 级,D 层已完成。<br>- 升降机:在 C 和 D 塔中继续安装塔式升降机,E 塔中的电梯正在调试中。<br>- 垃圾槽:在塔 C D E 中全部完成。<br><br>劣质配型<br>- 石膏:5层6至14级螺柱工程已完成,6-13 P60外墙在进行中;等级 6 - 10 内部石膏正在进行中;塔 4 螺柱工程到 6 级 - 12 级已完成;<br>塔 3 螺柱工程到 6 级 - 13 级完成.<br>- 防水:<br>在 6 楼 C 层的阳台和播种箱的熨平板和防水。<br>在 14 层 D 层的阳台和播种箱的熨平板和防水。<br>- 绘画:在E塔7至16层的阳台区域完成天花板纹理涂料;<br>从 C 塔的 7 层到 16 层的阳台区域完成天花板纹理涂料。<br>- 阻塞工作:服务提升器块工作完成,从15级到16级;<br>- 绿色立面:平台级汽车预熟植物已经开始。<br>- 瓷砖:定于本周一结束在5号塔。<br>- 厨房:6级 - 7级机柜时间表,交付到现场本月底<br><br>要查看照片,请单击以下链接: https://www.mdkholding.com/copy-of-riverina-pcg-june-2019<br><br>通知将提供时,从建设者实际完成,届时我们将开始银行估值和最终买家检查。<br><br>* 时间表如有更改,恕不另行通知。<br> <br>延迟结算后果<br>一旦和解被触发,您将只有有限的时间来结算您的财产。如果您没有按时结算,将收取罚款,供应商同意的奖励可能会撤销。<br><br>最热烈的问候,<br>杰西卡·伊伊<br>结算团队
正在翻译中..
结果 (简体中文) 3:[复制]
复制成功!
窗户和立面<br>-幕墙<br>-现浇混凝土已从6层安装到C塔13层;<br>-现浇混凝土已从6层安装到D塔16层;<br>-北立面幕墙已安装7层至13层;<br>-东立面幕墙已安装7层至13层;<br>滑动门<br>-C座6层至16层外部框架已完工;<br>-C座6层至16层的内部框架已完工;<br>-D座外部框架已从6层完成至15层;<br>穿孔筛网<br>-钢框架和支架已在E塔14至16层安装60%;<br>-折叠穿孔筛网将从E座14层至16层完成;<br>-折叠穿孔筛网将从C塔的14层至16层完成;<br>铝包层<br>-铝包层从E座西侧立面的6层安装到13层;铝包层从D座东侧和西侧立面的6层安装到13层;铝包层从C座东侧立面的6层安装到13层;铝包层从1层安装到5层在C座西南角;<br>-栏杆底部轨道已安装在E座7层-13层。<br>服务<br>-在9-14层,E塔,9-13层,D塔上安装冷热水和煤气管道。<br>-机械:在8-13层,E塔,8-12层,D塔上安装管道和制冷管。<br>-电气:C D E塔,粗加工,8-12层完工。<br>-消防服务:在C&D塔上安装10层至16层的喷水管,6层至18层的消防栓,D塔完工。<br>-电梯:正在进行C&D塔楼电梯的安装,E塔楼电梯正在调试中。<br>-垃圾斜槽:斜槽部分全部安装在C D E塔内。<br>劣质装修<br>-抹灰:完成5号楼6层至14层柱头工程,正在进行6-13层P60外墙;正在进行6-10层内部抹灰;完成4号楼6层至12层柱头工程;<br>完成3号塔6层-13层的螺柱工程。<br>-防水:<br>C座6层阳台和花盆箱的找平和防水。<br>D座14层阳台和花盆箱的找平和防水。<br>-油漆:E座7层至16层阳台区域完成吊顶纹理油漆;<br>C座7层至16层阳台区域完成的天花板纹理油漆。<br>-砌块工程:从15层到16层的服务立管砌块工程;<br>-绿色门面:已开始种植平台级汽车标准杆。<br>-瓷砖:计划于本周一在5号楼开始。<br>-厨房:6层-7层橱柜计划于本月底交付至现场<br>若要查看照片,请单击以下链接:https://www.mdkholding.com/copy-of-riverina-pcg-june-2019<br>通知将在实际竣工时提供,从建造者,在这一点上,我们将开始银行估价和最终买方检查。<br>*时间表如有更改,恕不另行通知。<br>延迟结算的后果<br>一旦触发结算,您将只有有限的时间结算您的财产。如果您不按时结算,将收取罚款,并可能撤销供应商同意的奖励。<br>致以最热烈的问候,<br>叶茜茜<br>结算小组<br>
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.

Copyright ©2024 I Love Translation. All reserved.

E-mail: