Precast foundation: C30 concrete, size 2 * 2 * 0.5m.. The spacing between foundation columns is 6-10m. Angle steel L50*50*5 is used for edge sealing of prefabricated foundation corners, two embedded rings of HPB235φ20 steel bars are embedded at the top, and antirust paint is painted on the angle steel. Two DN100 steel pipes are reserved in the middle for hoisting holes. The concrete cushion block needs to be buried with cross-shaped flat steel, which is used to weld the stop to fix the bottom plate of the column. When casting the lifting hole and reserved flat iron position, it shall be determined according to the actual situation on site. Consider adding at least 20 basic maneuvers. At least 424 foundations need to be prefabricated on site according to this specification.