6. Open the Task Properties Cost Totals tab. You will see that there are both Resource and Direct Costs assigned to the task. There are no Actual Costs yet since the task is still in the Planned Status.
6. Open the Task Properties Cost Totals tab. You will see that there are both Resource and Direct Costs assigned to the task. There are no Actual Costs yet since the task is still in the Planned Status.