The excavated foundation pit groove should be promptly sealed and equipped with a water pump for drainage to prevent it from being soaked in water. At the same time, the construction of most of the main bridge pile foundations should be completed quickly to ensure safe flood crossing. After the flood period, the main bridge bearing platform and pier body should be constructed quickly.<br>During the rainy season, concrete and masonry work should strictly follow construction specifications.<br>Both the mixing station and the sand and gravel silo should be provided with rain shelters, while the pier and abutment concrete construction should be provided with water shelters. Weather forecasts should be kept in mind at all times, and pouring concrete should be avoided as much as possible on rainy days.<br>Strengthen the observation of deep foundation pits, deep cutting slopes, and safety inspections during rainy and flood seasons such as adjacent highway and railway construction.