Due to the preparation of the effect drawing and section drawing in recent days, this drawing has been delayed a little bit. At present, the foundation drawing of the chimney has been completed. Now we are working overtime in translation, and the translation is expected to be completed at least tomorrow.The foundation drawing of the annealing section is still being designed overtime, which will be delayed for a few days.At the same time, because the previous drawing time was really compressed to the extreme, mainly to meet your construction rhythm before the rainy season as much as possible, it is impossible to achieve according to the normal design cycle.It has not been long since the general layout was confirmed, so it is really not guaranteed to be 100% all the time.Now all the designers are working overtime to rush for the deadline. If there is a slight change in the process, it may be delayed slightly. We hope you can understand us more. We're doing the best we can. Thank you