During the first 2 months of the handover period, the Main Contractor shall set up one Special Team (貼身服務隊) comprising of 木器, 水喉, 鋁窗, 油漆, 雲石打磨, 泥水 (6 workers per team) for every 200 units. The Special Teams shall be under direct instruction of Handover CS Team/ the Employer during these 2 months and should not overlap any workforce for other rectification works. These special teams shall be assigned to attend urgent and hot cases.