The critical path network or equivalent shall be computerized by CONTRACTOR and the methodology shall be laid down to obtain the necessary inputs required to maintain the printout and deviations on a monthly basis. The critical path network itself or equivalent and all supporting documents shall be changed or modified as necessary and reissued with the modifications as soon as slippage on any one item has exceeded 10% of the time allowed for that item. Computerized printout indicating all activities and the float shall be submitted to OWNER by CONTRACTOR on a monthly basis.