I am the project manager in the project, and the goal of the project is to complete the delivery of the project shop by June 30, 2019. The construction plan of the whole project shall be prepared according to the delivery target. On this basis, material purchase plan, cost control plan, quality control plan, safety control plan and resource allocation plan are prepared. The whole project is divided into underground foundation stage, ground main body stage and decoration stage, and node control plans are prepared respectively. In the construction process, the node plan is the control core. Compare the actual construction period with the planned construction period. Take corresponding measures to remedy the deviation. The final project is completed in advance for filing, and the delivery is completed smoothly. I learned from this project that making a feasible plan is the premise, building an excellent team is the guarantee of success, and the control and correction in the process are the measures to ensure the goal.<br>