5. Select Planned Finish and enable Apply to All.6. All selected tasks will be given the status of Finished.7. Assume a rain delay caused the Roof task to start later than planned. Select the Roof task under Envelope8. In Task Properties window General tab Progress, change the Status from Planned to Finished.9. The Task Start Time window appears for the task Roof. Select Choose Date then click the “C” button to open the calendar and choose 21 April 16 as the Actual Start.10. The Task Finish Time window will appear. Select Predicted Finish. This will use the Actual Start date you just chose and the Planned Duration to calculate the Actual Finish date.