3.3 The consultants shall commence Schematic, Detail Development soon after confirmation of appointment. The construction drawings are to be produced concurrently with design stages to obtain Construction Permits and other relevant approvals/certificates in 2020.Milestone activities Date 1.Commencement of piling/ Excavation and Lateral Support April 20202. Acquisition of construction permit mid 2020 3. Commencement of structure (pile cap, basement and super-structure) July 20204. Completion of project End 2024 or earlierWhile the above timeline is indicative of milestones schedule and adjustment may incur from time to time depending on site conditions and no claim for additional fee will be entertained due to milestone revision. The timeline indicates that the project will proceed on very fast-track basis and the following sets of drawings including mockup rooms will be prepared simultaneously:-a. Design drawings/specification b. Tender documentation c. Major submission drawings/document