Thanks for your update, the efficiency improving target is quite encouraging!
1. Could you pls advise you plan to meet below mentioned target by when? I have added 1 column (Deadline to achieve the target) into your excel, pls fill the date according to your plan.
2. I have deleted Yeezy 700 because the production is not in APE.
3. For Yeezy 700 V3, as it’s still in PT stage, let’s try be figure out the best set up (including layout, tools/jigs, automation, VSM, etc) through the PT so that bulk production can start with the optimized setup.
4. It seems currently you don’t have any improving plan for stockfitting, why?