Hi Chris and DafeBefore the afternoon meeting, we have some comments below for the electric renovation work this weekend, need you to do some rectification in the work steps:• For air-condition units in comms closet rooms 1205 and 1227 and 1333, no need to power down both WSHP unit and VRV unit, generally we run the WSHP unit with VRV unit standby, so only power off the VRV. Note: Before the work, local team need to notice CS command center because the TMS alarms will be triggered when do the power off. • Important reminder: in construction area, before switch on the breakers, especially the UPS power, please provide the test report to MS onsite engineer, this is to prevent any potential power trip risk.• For the electric modification work on power box BUS-JV-N1, no need to shut down total power, this will impact power supply of SJV office area, only need to power off the breakers that involved under which the cable need to be relocated. For other detail, we can talk about on the today meeting.