仓库地基处理设计要求:工后沉降≤10m,则施工沉降量必须≥370.3mm; 表层土体经强夯或碾压后地基承载力 fak≥120kPa;地基处理的英语翻译

仓库地基处理设计要求:工后沉降≤10m,则施工沉降量必须≥370.3m

仓库地基处理设计要求:工后沉降≤10m,则施工沉降量必须≥370.3mm; 表层土体经强夯或碾压后地基承载力 fak≥120kPa;地基处理交工标高按 1.3 条 要求控制。采用处理方法:“真空水载联合预压+冲击碾压联合技术”,即主要采用真 空预压+覆水堆载+冲击碾压法。本场地地基处理范围按每边外扩且兼顾周边道路等,地基处理面积约 32560m2,分一个处理区,处理深度约现地表下 20m,竖向排水体设置到③2 层 为砂质粉土层底面。覆水深度平均为 2.0m。地基处理前在现地表回填 1.0m 厚 素填土。计算表明,在 80kpa 真空荷载、2m 覆水荷载及 1.0m 回填土荷载作用下, 对原状地基土,总预压荷载为约 116kpa,远大于使用荷载下 85.65kpa 的附加荷 载,形成超载预压。
0/5000
源语言: -
目标语言: -
结果 (英语) 1: [复制]
复制成功!
The design requirements for the foundation treatment of the warehouse: after the construction is ≤10m, the construction settlement must be ≥370.3mm; the bearing capacity fak≥120kPa of the surface soil after dynamic tamping or rolling; the foundation elevation of the foundation treatment is controlled according to 1.3 requirements. <br>The treatment method is adopted: "vacuum water-loaded combined preloading + impact rolling compaction technology", that is, vacuum preloading + water-covered stacking + impact rolling compaction method is mainly used. <br>The ground treatment scope of this site is expanded on each side and taking into account the surrounding roads. The ground treatment area is about 32560m2, divided into a treatment area, the treatment depth is about 20m below the current surface, and the vertical drainage body is set to ③ 2nd layer is the bottom surface of sandy silty layer . The water-covering depth is 2.0m on average. Before foundation treatment, backfill 1.0m thick plain fill on the current surface. <br>The calculation shows that under the action of 80kpa vacuum load, 2m overlying water load and 1.0m backfill soil, the total preload of the undisturbed foundation soil is about 116kpa, which is much larger than the additional load of 85.65kpa under the applied load, forming an overload preload.
正在翻译中..
结果 (英语) 2:[复制]
复制成功!
Warehouse foundation processing design requirements: after the settlement of the work of 10m, the construction settlement amount must be 370.3mm;<br>The treatment method is used: "vacuum water-borne joint pre-pressure-impact crushing joint technology", that is, the main use of real-air pre-pressure and cover water pile-load-and-impact crushing method.<br>The site foundation processing range according to each edge expansion and take into account the surrounding roads, the foundation processing area of about 32560m2, divided into a processing area, processing depth of about 20m below the surface, vertical drainage body set to (3) 2 layers for the sand soil layer bottom. The average water cover depth is 2.0m. The foundation is backfilled with 1.0m thick soil before the surface is treated.<br>The calculation shows that under the action of 80kpa vacuum load, 2m cover load and 1.0m backfill load, the total pre-pressurized load for the original base soil is about 116kpa, which is much larger than the additional load of 85.65kpa under the load, resulting in overloadpreed pre-pressure.
正在翻译中..
结果 (英语) 3:[复制]
复制成功!
Design requirements for warehouse foundation treatment: if the post construction settlement is ≤ 10m, the construction settlement must be ≥ 370.3mm; the bearing capacity of the surface soil after dynamic compaction or rolling is FAK ≥ 120kPa; the handover elevation of the foundation treatment shall be controlled according to the requirements of article 1.3.<br>The treatment method: "vacuum water load combined precompression + impact rolling combined technology", that is, vacuum precompression + covered water surcharge + impact rolling method is mainly used.<br>The foundation treatment scope of the site is expanded on each side and the surrounding roads are taken into account. The foundation treatment area is about 32560m2, divided into one treatment area, the treatment depth is about 20m below the surface, and the vertical drainage body is set to the bottom of layer ③ 2, which is sandy silt layer. The average covering depth is 2.0m. Before foundation treatment, 1.0m thick plain fill shall be backfilled on the surface of the site.<br>The calculation shows that the total preloading load of the undisturbed foundation soil is about 116kpa under the action of 80kPa vacuum load, 2m water cover load and 1.0m backfill load, which is far greater than the additional load of 85.65kpa under the service load, forming the overload preloading.<br>
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.

Copyright ©2024 I Love Translation. All reserved.

E-mail: