1. All the CPU card of PLC are not found on site. Which box are they in? The CPUs haven’t been shipped yet. They were used for the tests of SW at our facilities. In our opinion it’s much better to ship them just before the SW engineer will come to site.2. Some electrical drawings of PK were not found 2.1 PK-260 You can find the electrical drawing in the manual of the equipment. Please see into the share point, folder “02 By email/by EGT/2020-01-31 Manuals/PK-260/file 01.C3544 – Final book_Rev.2” 2.2 PK-420 You can find the electrical drawing in the manual of the equipment. Please see into the share point, folder “02 By email/by EGT/2020-01-31 Manuals/PK-420/file 04.ITAS_42064_EN” 2.3 All burners F710 / 790, f711 / 791 You can find the electrical drawing in the manual of the equipment. Please see into the share point, folder “02 By email/by EGT/2020-03-31 Manuals/F-710_03/14.2 ESA Electrical documentation/2 Wiring diagram” 3. Now we think that it will take a long time to complete the installation of CX system, so we want to finish the installation of pk820 first and then start pre commissioning. So please send PLC and software of LCC