Up to yesterday, we have successfully removed all the four filters left in the natural gas pipeline. This afternoon, we have also completed the connection and air tightness test of all the flanges. Therefore, it is planned to restart the moisture test of natural gas pipeline at 10 a.m. tomorrow. In view of the insufficient nitrogen pressure and flow on our side, we may not be able to meet the moisture test, so we still want you mlng to introduce nitrogen for purging to our side. Please help to coordinate this plan. Thank you.<br>