The simple flow chart for the positioning of the floor line is: confirm the first-level control point on the ground floor → vertically project the first-level control point on the ground floor to the floor → pop-up the first-level control network of the floor → review the first-level control network of the floor with the check point of the first-level control line of the floor → pop-up beam Column secondary control line→determine the position of the third-level review point of the side ring beam→after the bottom mold of the side ring beam is in place, use the third-level review point to review the position of the side ring beam.