After vacuum preloading is unloaded, the outline of the plant building (the side line is expanded by 2 m, 20048.4 m2) is backfilled with silty sand or silt to +4.600 m in layers of 50 cm, and the backfill soil is subjected to dynamic compaction and vibration rolling deal with. After the other areas are backfilled to the design elevation, vibration rolling is performed. <br>The dynamic tamping adopts two full tamping treatments, a flat hammer with a ram diameter of 2.0 ~ 2.5 m. Click tamping energy 800 KN · M, 1 hit per point; after full tamping is completed, level the site and perform vibration rolling. The construction parameters of vibration rolling are as follows: