8. The new baseline will be listed in the Navigator Scheduling panel Baselines and Scenarios window. In the current schedule, the critical path tasks are white outlined in red, whereas tasks not on the critical path are green as shown below. The Baseline is directly over the current schedule, with critical tasks in solid blue, and non-critical tasks outlined in blue but hollow.