To November 25, 2019 the progress of the project site as follows: <br>1, refining region: In addition to cooling towers PK870 foundation did construction, Mcc-4 construction steel no other basis for the completion of civil construction. Complete refining installation platform, MC820, PK820 (box), C830 installation; <br>2, smelting area: PK731 no expanse distribution chamber, PK820 distribution chamber doors not installed. Complete rail mounting, MC720,721 installation, PK720,721 mounting chassis; <br>3, crushing zone: Complete + 4, + 8m building construction, MCC-1 is not installed windows, but the basic construction chamber Cx no ground construction, H-201 / V201 column did construction, other civil foundation to complete the construction. C530 complete the installation. <br>4, crystalline regions: section beams arrived at the scene, on the 5th of December to complete the plan 10.5m following installation. <br>5, the production plant: plant area AX cross shaft 27-39 and a top wall insulation is completed, the window portion is completed.