PRFC Status will be validated as per the process detailed in the section 2.3.2 above for those Sub-systems and/or part thereof where a partial commissioning scope is planned (e.g. execution of MOP leak test, energisation of lighting circuits…). In this case, the PRFCC will be issued and duly signed off after the corresponding walkdown, validation of PRFC booklet and close-out of outstanding 0A punch items as defined in before mentioned section.