1. The keys for the tipper had been lost. 2. Vehicle was jump started causing damage resulting in a hydraulic leakage.3. Without prior notification the vehicle was placed in MCT Mombasa CFS.4. CFS of our choice would have resulted in a minimum free period of 30 days maximum 90 days.5. Shipping line had logged in two separate entries, one for the truck and one for the tires on board the truck opposed to one entry for both. 6. MCT Mombasa is demanding 4,463 USD for storage and demurrage charges.