Surface settlement monitoring <br>The settlement amount of soft soil layer under pre-pressurized load and its development process with time are monitored. On the one hand, it can be used to evaluate the safety and rationality of the loading rate, to prevent the soft-base instability caused by the loading rate too fast, on the other hand, the actual solidity of the soft base can be calculated by analyzing the observation results, the settlement value of the foundation work can be calculated and the reasonable unloading time is determined. Number of settlement observations: The settlement observation point slots on about 2000 m2 to set one, a total of 15 set.