If Party B believes that the project has met the completion acceptance conditions agreed in Clause 37.1, Party B shall notify the supervising engineer, general contractor, and Party A accordingly. All parties shall carry out the completion acceptance according to the agreement of this article. Party B shall notify the supervision engineer of a certain date at least 21 days in advance, stating that the project will meet the conditions for completion acceptance after that date, and provide Party A with a copy. This date is referred to in this paragraph as the "application date for completion of construction inspection".