□ Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS) in red quantifies the budgeted value of the planned work to date on the selected task or group of tasks. The total Planned Value of the task at the end of the task is also referred to as the Budget at Completion (BAC). The intersection of the Focus Time line with the red PV line reflects the Planned Value at that point in time for a selected task or group of tasks. This cost is shown in red on the left of the EVA Graph. Moving the Focus Time gives a cost forecast reading at that specific moment in time for the selected task or group of tasks.□ Earned Value (EV) or Budgeted Cost of Work Performed (BCWP) in grey quantifies the budgeted value of the work performed to date on the selected task or group of tasks. The intersection of the Data Date line and the grey EV line reflects the Earned Value at that point in time for the selected task or group of tasks.□ Actual Cost (AC) or Actual Cost of Work Performed (ACWP) in blue quantifies the actual cost incurred for the work performed to date on the selected task or group of tasks.□ Baselined Cost (BL) in green quantifies the Planned Value saved with the selected Baseline on the selected task or group of tasks.NOTE: You can show/hide Planned Value (PV), Earned Value (EV), Actual Cost (AC) and/or Baselined Cost (BL) using the tick boxes in the Legend.