When pouring the underground foundation, the temporary observation points shall be buried according to the settlement observation points and positions determined in the design, and the first settlement observation shall be conducted. The whole foundation pouring shall be completed at least twice. When it reaches ± 0.000, the permanent settlement observation points shall be buried according to the design requirements, and the observation shall be conducted once for each additional layer or load, so as to maintain the continuity of settlement observation. After each observation, the settlement and cumulative settlement are calculated by the measuring unit, so as to grasp the average settlement and the differential settlement between each point in time, and draw the measurement results into the settlement observation results table.<br>