there is a certain category of rights in the context of change approval. In order to be efficient in change process and reduce throughput times, the fast-track method is also used in additionto the full-track method. If the Fast Track criteria’s were fulfilled, then the CR is immediately approved by the CCT (CPB & CCB were skipped / CIB takes place in normal way). The decision about the fast track or the full track is delegated by the change manager by using a decision matrix (which is already implemented in the CCT) – see attached presentation. Martin & Tinawill assist you on further questions. Any questions – just let me know … regards Joerg