主变容量一般根据变电站建成后5-10年的短期负荷规划来选择,并适当考虑10-15年的长期负荷发展。对于郊区变电站,主变容量应与城市规划相结合的英语翻译

主变容量一般根据变电站建成后5-10年的短期负荷规划来选择,并适当考虑

主变容量一般根据变电站建成后5-10年的短期负荷规划来选择,并适当考虑10-15年的长期负荷发展。对于郊区变电站,主变容量应与城市规划相结合。为了长远利益,电站应根据近期和远期总负荷选择主变容量,对于有重要负荷的变电站,应根据负荷性质和电网结构确定主变,应考虑一台变压器停用时,另一台变压器容量应在过载能力允许的时间内,以保证用户的一次和二次负荷。因此,每台变压器的额定容量为Sn=7.0pm,其中PM为变电站的最大负荷选择,即Sn=0.7×38.77=27.14kva。当一台变压器停止运行时,70%的负荷也得到保证。由于一般电网变电所的非重要负荷约占25%,为保证变电所的重要负荷,用Sn=7.0pm计算主变容量是可行的。经计算可选用额定容量为31.5MVA的主变压器。为了保证供电的可靠性,避免一台主变失灵或检修对供电的影响,一般在变电所内安装两台主变。安装三座或三座以上变电站,提高了变电站的可靠性,但接线网络复杂,增加了投资。同时,配电设备和电力保护的复杂性增加,维护和开关操作的复杂性也增加。考虑到两台主变压器同时发生故障的概率较小,适合长期负荷增长和扩大,因此本变电站两台主变压器的选择完全满足要求。
0/5000
源语言: -
目标语言: -
结果 (英语) 1: [复制]
复制成功!
The main transformer capacity is generally selected according to the short-term load planning of 5-10 years after the completion of the substation, and the long-term load development of 10-15 years is appropriately considered. For suburban substations, the main transformer capacity should be combined with urban planning. For long-term benefit, the power station should select the main transformer capacity according to the total load in the near and long term. For the substation with important load, the main transformer should be determined according to the nature of the load and the grid structure. When one transformer is out of service, the capacity of the other transformer should be considered. It should be within the time allowed by the overload capacity to ensure the user's primary and secondary load. Therefore, the rated capacity of each transformer is Sn = 7.0pm, where PM is the maximum load selection of the substation, that is Sn = 0.7 × 38.77 = 27.14kva. When a transformer stops operating, 70% of the load is also guaranteed. Since the non-important load of the general power grid substation accounts for about 25%, in order to ensure the important load of the substation, it is feasible to calculate the main transformer capacity with Sn = 7.0pm. After calculation, the main transformer with rated capacity of 31.5MVA can be selected. In order to ensure the reliability of the power supply and avoid the failure of one main transformer or the impact of maintenance on the power supply, two main transformers are generally installed in the substation. The installation of three or more substations improves the reliability of the substation, but the wiring network is complicated, which increases investment. At the same time, the complexity of power distribution equipment and power protection has increased, as has the complexity of maintenance and switching operations. Considering that the probability of two main transformers failing at the same time is small and suitable for long-term load growth and expansion, the selection of two main transformers in this substation fully meets the requirements.
正在翻译中..
结果 (英语) 2:[复制]
复制成功!
The main variable capacity is generally selected according to the short-term load planning of 5-10 years after the completion of the substation, and the long-term load development of 10-15 years is given due consideration. For suburban substations, the main variable capacity should be combined with urban planning. In the long-term interest, the power station should choose the main variable capacity according to the near-term and long-term total load, for substations with important load, should be based on the load nature and power grid structure to determine the main change, should consider the retirement of one transformer, another transformer capacity should be in the overload capacity allowed time, to ensure that the user's first and secondary load. Therefore, the rated capacity of each transformer is Sn . 7.0pm, where pm is the maximum load selection for the substation, i.e. Sn s n.s. 38.77 x 27.14kva. When a transformer stops operating, 70% of the load is guaranteed. Since the non-essential load of the general power grid substation is about 25%, it is feasible to calculate the main variable capacity by Sn s 7.0pm in order to ensure the important load of the substation. The main transformer with an optional capacity of 31.5MVA is calculated to be available. In order to ensure the reliability of power supply, to avoid the failure of a main change or the impact of maintenance on the power supply, generally installed in the substation two main changes. The installation of three or more substations has improved the reliability of the substations, but the complex wiring network has increased investment. At the same time, the complexity of power distribution equipment and power protection increases, as does the complexity of maintenance and switching operations. Considering that the probability of two main transformers failing at the same time is small, suitable for long-term load growth and expansion, the choice of two main transformers in this substation is fully satisfied.
正在翻译中..
结果 (英语) 3:[复制]
复制成功!
The main transformer capacity is generally selected according to the short-term load planning of 5-10 years after the completion of the substation, and the long-term load development of 10-15 years is properly considered. For suburban substation, the main transformer capacity should be combined with urban planning. For the long-term benefit, the power station shall select the main transformer capacity according to the total load in the near and long term. For the substation with important load, the main transformer shall be determined according to the load nature and grid structure. When one transformer is out of service, the capacity of the other transformer shall be within the time allowed by the overload capacity to ensure the primary and secondary load of the user. Therefore, the rated capacity of each transformer is Sn = 7.0pm, in which PM is the maximum load selection of the substation, that is, Sn = 0.7 × 38.77 = 27.14kva. When a transformer stops running, 70% of the load is also guaranteed. Because the non important load of general Grid Substation accounts for about 25%, in order to ensure the important load of substation, it is feasible to calculate the main transformer capacity with Sn = 7.0pm. The main transformer with rated capacity of 31.5MVA can be selected after calculation. In order to ensure the reliability of power supply and avoid the influence of one main transformer failure or maintenance on power supply, two main transformers are generally installed in the substation. The installation of three or more substations improves the reliability of the substation, but the connection network is complex and increases the investment. At the same time, the complexity of distribution equipment and power protection increases, as well as the complexity of maintenance and switch operation. Considering that the probability of two main transformers failure at the same time is small, it is suitable for long-term load growth and expansion, so the selection of two main transformers in this substation fully meets the requirements.<br>
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.

Copyright ©2024 I Love Translation. All reserved.

E-mail: