Land for all four projects has been secured and land leases (29 years) are ready to be formally signed;All to be connected to HV line (150Kv);Pre-feasibility analysis completed;Projects 48 and 108 could be built with single-ax trackers; Project 45 already has an interconnection offer.Compensation for all the solar parks will be achieved through private PPAs.Italian market is very sophisticated and liquid when it comes to construction of renewables and construction/project financingPermitting timetable: 12-18 months from start of permitting process to RTB statusIrradiance in Sicily is in the 2000 KWh/m2 range