According to the conditions of this project, 6t ~ 10t rollers are used to lay the foundation pits for compaction and no sectioning is allowed. The number of tamping or rolling passes is determined by field test. It is planned to first static pressure twice, vibration rolling not less than 4 times, the roller is strictly prohibited to use vibration within 5m from the adjacent building, only static pressure, static pressure variable not less than 10 times. The rolling speed is planned to be 40m / min, and the overlapping width of the rolling track is not less than 50cm. The edges and corners should be compacted by manual or frog-type ramming machines.